HOW CONSTRUCTION
LOANS WORK

Construction lending is fundamentally different from a standard mortgage. Here's everything you need to understand — from pre-approval through permanent conversion.

Start the Process

WHAT MAKES CONSTRUCTION
LENDING DIFFERENT

Most borrowers understand how a standard mortgage works. Construction lending has a different structure, different risk profile, and different documentation requirements. Here's the comparison.

FeatureStandard MortgageConstruction Loan
CollateralExisting homeLand + construction costs
FundingLump sum at closingDown payment / equity + milestone draws
Payments during buildN/AInterest-only on drawn funds
Appraisal basisCurrent market value"As-completed" value
UnderwritingBorrower onlyBorrower + project + builder
ClosingOne closingOne loan, two phases: temporary & permanent
Free Float DownNoYes
Timeline30–45 days to close30–45 days to close + 6 months plus build

HOW DRAWS WORK

Funds are not released all at once. They're disbursed in stages tied to completed construction milestones — verified by an independent inspector. This protects you, your builder, and the lender.

Draw 1
Lot, Permit & Pre-Construction
Typical %
~12%
Timing
Released at loan closing
Covers
Covers the cost of the lot, permit fees, and all pre-construction expenses. This draw is released the day the loan closes so your builder can mobilize immediately.
Draw 2
Foundation & Underground Trades
Typical %
~12%
Timing
After foundation inspection
Covers
Released once the foundation is poured and all underground trades — plumbing, electrical conduit, and HVAC rough-in below slab — are completed and inspected.
Draw 3
Rough Framing Complete
Typical %
~19%
Timing
After framing inspection
Covers
Released once rough framing is completed. Includes structural walls, roof framing, sheathing, and exterior wrap. Inspector verifies the frame is plumb, square, and weather-tight.
Draw 4
Intermediate Mechanicals
Typical %
~20%
Timing
After mechanical rough-in inspection
Covers
Released once intermediate HVAC, plumbing, electrical, and insulation have been completed. All rough-in work must pass inspection before this draw is processed.
Draw 5
Drywall, Stucco & Interior Paint
Typical %
~20%
Timing
After drywall & stucco inspection
Covers
Released once drywall is hung and finished, exterior stucco is applied, and interior painting is complete. This milestone marks the transition from rough to finish work.
Draw 6
Final Finish & Certificate of Occupancy
Typical %
~16%
Timing
After CO is issued
Covers
Final draw released once flooring, cabinets, countertops, plumbing trim, electrical trim, HVAC trim, and exterior paint are complete — and the Certificate of Occupancy has been issued by the local jurisdiction.
Draw Inspection Process: Before each draw is released, an independent inspector visits the site to verify the work is complete and meets the required standard. This typically takes 2 to 5 business days. Your builder should plan for this inspection window in their schedule.

TYPICAL ARIZONA CUSTOM HOME TIMELINE

Building a custom home in Arizona usually happens in two distinct phases: planning before closing and construction after closing. In many cases, pre-construction planning takes 2 to 4 months, followed by 8 to 12 months of construction, depending on the builder, permitting, design complexity, inspections, and weather.

Understanding that difference helps set realistic expectations around timing, draw activity, and when the home is expected to be complete.

Before Closing
Typically 2–4 months

Pre-Construction Planning

  • Initial consultation and financing review
  • Loan application and pre-approval
  • Builder selection and vetting
  • Architectural plans and specifications finalized
  • Budget, contract, and project scope reviewed
  • Permit application submitted
  • Appraisal, underwriting, and final loan approval
  • Loan closes and construction begins
After Closing | Months 1–3

Site Work, Foundation & Framing

  • Site clearing and grading
  • Excavation and foundation work
  • Foundation inspection and first major draw activity
  • Framing begins
  • Roof structure completed
  • Framing inspection and subsequent draw released
After Closing | Months 4–8

Mechanicals, Exterior & Dry-In

  • Rough plumbing, electrical, and HVAC
  • Windows and exterior doors installed
  • Roofing completed
  • Exterior stucco or siding progresses
  • Rough-in inspection completed
  • Insulation installed
  • Drywall hung and finished
After Closing | Months 8–12

Interior Finish & Completion

  • Cabinets and countertops installed
  • Flooring installation
  • Fixtures and appliances set
  • Interior paint and finish work completed
  • Landscaping and final grading
  • Final inspections completed
  • Certificate of Occupancy issued
  • Loan converts to permanent financing

Note: Every project is different, and timelines can vary based on permitting, builder scheduling, material availability, weather, and change orders. This overview is intended to provide a realistic framework for how a typical Arizona custom home progresses from planning to completion.

INTEREST DURING CONSTRUCTION

During the construction phase, you pay interest only on the funds that have actually been drawn, not on the full loan amount. That means if your total loan is $600,000 but only $200,000 has been disbursed, your interest payment is based on the $200,000 outstanding balance.

In the early stages of the project, the borrower's required funds are generally used first before construction loan proceeds are fully disbursed. This can help keep the outstanding loan balance lower at the beginning of the build. In some cases, the first draw at closing may be used to pay for the land. A limited draw at closing may also be allowed to prepay for materials and lock in pricing, although draws at closing are generally limited to 10% of the contract budget.

As construction moves forward and additional draws are released, the outstanding balance increases, and the monthly interest payment rises accordingly. By the end of the construction phase, interest is typically being paid on the full amount advanced.

Once construction is complete, the loan converts to the permanent mortgage, and the payment changes from interest-only to principal and interest based on the final loan terms.

This structure helps keep payments lower during the early phase of construction, which can make cash flow more manageable while the home is being built.

~10% disbursed
Lower interest-only payment
Interest is charged only on funds disbursed — early payments are at their lowest.

Illustrative only. During construction, payments generally reflect interest on funds disbursed. After completion, the loan converts to permanent financing. Actual payments depend on final loan amount, note rate, term, escrow setup, and draw timing.

CONSTRUCTION TO PERMANENT
LOAN GUIDE

Our complete borrower guide covers builder activation, the draw process, progress inspections, cost overages, payments, the rate float-down, and loan conversion — everything you need to navigate a construction loan with confidence.

Download the Guide

PDF · Free · No signup required

LET'S BUILD YOUR PLAN

Now that you understand how construction lending works, let's apply it to your specific project. Reach out and we'll map out your loan structure, timeline, and draw schedule.